The completed detention pond encompasses approximately one acre. The approved Certify Survey Map (CSM) is provided below. The detention pond is necessary to treat stormwater that flows from the Olde Apple Acres development. Stormwater is routed south through the dry pond and drainage easement located between Sheppard Road and Charlie Anna Drive and then south on Welsh Have Drive to the detention pond south of Omro Road. Much of the stormwater flowing into the detention pond will be captured by the storm sewer infrastructure to be installed when Omro Road is reconstructed. More specifically, Jones Pond will capture stormwater on a stretch of Omro Road from Leonard Point Road to just west of Cambria Court. Treated water from the pond will outfall to Honey Creek via the ditch on STH 21. This project is outlined in the Town’s 2018 Stormwater Management Plan.



Construction of the pond was completed in August 2020. Final plantings and landscaping will be finished in the Spring of 2021.
Jones Pond CSM-Sheet 1
Jones Pond Plan Set
Jones Pond Concept Plan